Planners and Developers

What can UKOPA provide to Planners and Developers

UKOPA has extensive knowledge and experience in the area of pipeline risk assessment. This knowledge has been codified in IGEM/TD/2 – Application of Pipeline Risk Assessment to the Proposed Developments in the Vicinity of High Pressure Natural Gas Pipelines, and PD 8010_3:2009 – Guide to the application of pipeline risk assessment to proposed developments in the vicinity of major hazard pipelines containing flammables.

The above documents can be used by pipeline operators and developers to assess the risks associated with proposed new developments from an existing pipeline. Pipelines which are classed as major accident hazard pipelines (MAHPs) under the Pipelines Safety Regulations 1996 are subject to land use planning controls and Local Planning Authorities are required to consult the HSE for advice regarding the acceptability of proposed developments on safety grounds in the vicinity of these pipelines.

The HSE’s advice has been codified in their PADHI (Planning Advice for Developments near Hazardous Installations) guidance and the Local Authority would take account of this advice when making a decision on the acceptability of a planning application. If the Local Authority does not allow the proposed development to proceed because of the advice in the PADHI guidance document then the developer can undertake a QRA (quantitative risk assessment) using the reference codes.

The QRA can be used to determine the additional risk at the location as a result of the proposed development. It should take account of any local features at the location that may reduce the risk such as sections of pipeline with greater wall thickness. The calculated risk levels can be compared with target measures of acceptable risk. If the risk levels appear to be high it is also possible to assess whether the risks can be further reduced through modifying the layout of the development or taking additional pipeline protection measures. Developers will need to discuss the practicality of applying these measures with the pipeline operator.

Why UKOPA will provide information to Planners and Developers

The codes and standards require that QRAs are carried out by experienced and competent personnel, and UKOPA will respond to requests from Planners and Developers for information and advice so that the recommendations of the codes and standards are applied in a consistent manner for all MAHPs, irrespective of the product transported.

This information and advice relates to the application of the recommended methodology and the use of risk mitigation measures. In the first instance the Planner or Developer should contact the relevant pipeline operator. UKOPA will aim to ensure that current operator best practice is made available to assist Planners and Developers in ensuring safe developments in the vicinity of MAHPs.

Risk Assessment Information and Advice that UKOPA can provide

The information and advice that UKOPA can provide is based on current operator best practice, and includes:

  • Quantified risk assessment methodology, data and techniques.
  • Reports and publications which describe current developments in quantifying major accident hazards.
  • A bi-annual report which details the number and cause of failures which have resulted in product releases from UK major accident hazard pipelines since 1971, including the exposure (i.e. number of kilometres of pipelines multiplied by number of years in operation). This data shows a reducing failure rate in UK pipelines over the period. The reasons for this are explained along with relevant data and observed trends. Insert link to the latest fault and failure report.
  • A report quantifying the damage that has occurred to UK major accident hazard pipelines but not resulted in failure. Also included are associated statistical parameters to support failure frequency predictive modelling. Insert link to the latest fault and failure report.

The UKOPA Risk Assessment Work Group (RAWG) will respond to requests for advice and information relating to quantified risk assessment of cross-country pipelines, for example:

  • Advice on calculation of failure rates based on data in the UKOPA database;
  • Advice on risk mitigation measures such as depth of cover, concrete slabbing and other methods;
  • Special risks, such as those posed by difficult construction e.g. wind farm structures, or construction risks;
  • Pipeline planning and hazard distances;
  • Training and competency requirements for pipeline risk assessors.

In addition, the RAWG can provide predictions of pipeline risk levels in accordance with the methodology defined in the codes and standards.

How can you get specific advice

The UKOPA Emergency Planning Workgroup (EPWG) will provide advice and information for any specific query, for example:

  • Advice on area-specific multi-party testing of emergency plans which aligns with current proposals for multiagency communication and response strategies required for the Civil Contingencies Act.
  • Information on the role and responsibilities of the Pipeline Emergency Response Officer (PERO) – the first operator representative in response to a pipeline incident.
  • Pipeline Emergency planning and hazard distances.
  • Training and competency requirements for pipeline emergency response.

Use of Pipeline Operational Data

The operational data collected by UKOPA allows:

1. Quantification of various mitigating effects

Particular examples are the effect of wall thickness, steel type, operating pressure, depth of cover, physical protection such as concrete slabbing, frequency of surveillance to prevent 3rd party damage. Extensive data collected for over 40 years for leak and damage events which have occurred on UK pipelines allows the effects to be assessed, and the relative risk reduction measures to be derived.

2. Predictive models for 3rd party failure rate to be developed

One major advantage of the damage data collected by UKOPA members is that the effect of 3rd party damage can be estimated for any combination of pipeline design factors. Analysis of this data and the effects the damage has had on the pipelines involved (depth of dents and gouges resulting from the damage) allows damage curves to be produced showing the limiting case for assessing pipeline failure. Combined with the frequency at which the damage has occurred (the hit rate), it is possible to apply fracture mechanics theory in such a way that the failure frequency can be predicted for all combinations of design parameters, even for cases where no failures have yet occurred.

3. Extensive analysis of leak and damage data to demonstrate the reducing failure rate trends, and identification of the reasons

The RAWG has sponsored extensive studies on the various failure mechanisms affecting cross-country pipelines. These demonstrate the reducing failure rate trends, particularly for mechanical defects and corrosion failure mechanisms.

In addition, and using the work carried out by the RAWG and FDMG, UKOPA has:

4. Sponsored derivation of Risk Reduction Factors for mitigation measures

Sometimes risk reduction measures are required when population encroachment has occurred during the lifetime of a pipeline. The original routing of the pipeline may have been well away from populated areas, but as time goes by, housing and other developments are sometimes constructed closer that the original design codes would have permitted. In such cases, risk reduction (mitigation) measures may be required. Quantification of the risk reduction effect of such measures is important to assess whether acceptable levels of safety can be achieved, even with these higher population levels.

The RAWG has sponsored studies to examine risk reduction measures such as concrete slabbing, thicker wall pipe, increased surveillance, and depth of cover, and published the findings in the risk codes IGEM/TD/2 and PD 8010 Part3.

5. The development of IGEM/TD/2 and PD 8010 Part 3

During 2005 UKOPA identified the need to formally publish pipeline risk assessment methodologies to provide transparency and consistency when undertaking these assessments, and this resulted in the publication of two new codes in January 2009:-

i. IGEM/TD/2 Application of pipeline risk assessment to proposed developments in the vicinity of high pressure Natural Gas pipelines

and

ii. PD 8010 Parts 3 – Code of Practice for Pipelines, Guide to the Application of Risk Assessment to proposed developments in the vicinity of major accident hazard pipelines containing flammables – Supplement to PD 8010 Part 1 2004

These Standards provide guidance for the risk assessment of developments in the vicinity of major hazard pipelines and are specific to the calculation of safety risks posed to developments in the vicinity of pipelines in the United Kingdom (UK) classed as major accident hazard pipelines, but the principles of the risk calculation are generally applicable to risk assessment carried out for other purposes. The guidance does not cover environmental risks.

The guidance in these standards are provided for the benefit of pipeline operators, local planning authorities, developers and any person involved in the risk assessment of proposed new developments in the vicinity of existing major accident hazard pipelines. They are based on the established best practice methodology for pipeline risk assessment, and are intended to be applied by competent risk assessment practitioners.

6. Integrity related aspects of pipeline operations

A number of sub-groups have been formed to investigate a number of pipeline integrity related issues. These include a group reviewing the effects of dents on pipeline operation, particularly where pressure-cycling may causes fatigue. This has produced best practice guidance with the aim of advising operators on how to assess dents (depth, location, severity etc.) and to further assess potential fatigue effects based on pressure cycling.

A further sub-group is examining best practice guidance relating to sleeves installed around pipeline sections at various locations such as road or rail crossings. Guidance on prioritising the assessment of the condition of sleeves, and techniques for repair or replacement, are being considered by this group.

Recent developments of wind farms has resulted in cases where plans to locate wind turbines close to pipelines have been proposed. A sub-group has considered recommended separation distances between pipelines and the location of wind turbines, and UKOPA has published guidelines based on these recommendations.

Who is the UKOPA Fault and Risk Assessment Working Group (FARWG))

The Fault and Risk Assessment Working Group (FARWG) provides information and expert opinion in a consistent manner with regards to pipeline fault data issues and pipeline risk assessment on behalf of UKOPA in relation to safety, security of supply and environmental issues. – Fault and Risk Assessment Working Group (FARWG)

Scroll to Top